Fiscal impact reports (FIRs) are prepared by the Legislative Finance Committee (LFC) for standing finance
committees of the NM Legislature. The LFC does not assume responsibility for the accuracy of these reports
if they are used for other purposes.
Current FIRs (in HTML & Adobe PDF formats) are a vailable on the NM Legislative Website (legis.state.nm.us).
Adobe PDF versions include all attachments, whereas HTML versions may not. Previously issued FIRs and
attachments may be obtained from the LFC in Suite 101 of the State Capitol Building North.
F I S C A L I M P A C T R E P O R T
SPONSOR Griego
ORIGINAL DATE
LAST UPDATED
1/29/07
2/26/07 HB
SHORT TITLE
Procurement Code Requirements
SB 555/aSFC
ANALYST Propst
APPROPRIATION (dollars in thousands)
Appropriation
Recurring
or Non-Rec
Fund
Affected
FY07
FY08
NFI
(Parenthesis ( ) Indicate Expenditure Decreases)
Relates to SB 264 and HB 277
SOURCES OF INFORMATION
LFC Files
Responses Received From
General Services Department (GSD)
Energy, Minerals and Natural Resources Department (EMNRD)
Public Education Department (PED)
Corrections Department (CD)
SUMMARY
Synopsis of SFC Amendment
The Senate Finance Committee amendment clarifies its application to state agencies, and not
local public bodies by striking “central purchasing office" and replacing it with “state agency."
The amendment also adds a new section to the Procurement Code that reads:
“Prior to submitting a bid or proposal for a state public works project, if the state purchasing
agent or a responsible bidder or a responsible offer or determines that there is only one source for
a specific service, construction or item of tangible personal property the is required in the
specifications, the state purchasing agent, responsible bidder or responsible offeror may require
any bid or offer submitted by a subcontractor or supplier to price separately the specific service,
construction or item of tangible personal property.
pg_0002
Senate Bill 555/aSFC – Page
2
This section that allows the state purchasing agent, or responsible offerors to determine that bid
specifications contain requirements that can only be met by a single source supplier, and to
require that bids from suppliers or subcontractors contain separate prices for those items. The
effect of this provision is to allow disclosure of sole source requirements and their cost to
offerors.
Synopsis of Original Bill
Senate Bill 555 adds a new section to the Procurement Code to allow multiple design service
contracts for multiple projects using a single qualifications-based request for proposals (RFP)
and multiple indefinite quantity construction contracts under a single request for proposals.
Dollar thresholds are a maximum of $50.0 per contract with architects and engineers with a
$200.0 cap over four years, and a maximum of $500.0 per contract for construction with a
$2,000.0 cap over four years. The Procurement Code section limiting use of multiple source
awards is amended to conform to this new authorization. Procurements under this new section
must:
State that multiple contracts may or will be awarded in the advertisement and the
RFP, as well as describe the services or construction to be performed.
Be a single selection process, except that each individual contract there is a separate
final list, and separate contract negotiation.
Result in contracts that do not exceed four years, including extensions and renewals.
Prohibit a contract award to a firm currently performing under a contract procured
under this section if the total amount of all contracts with the firm exceeds $200.0
over four years for architect/engineer services; or $2,000.0 for construction services.
The Property Control Act is amended to require prior State Board of Finance (SBOF) approval
only for construction contracts over $500.0. The public works project definition is raised from
$25.0 to $50.0.
FISCAL IMPLICATIONS
According to GSD, multiple source awards for design services contracts and indefinite quantity
construction contracts may streamline project administration for the Property Control Division,
and thereby save time and administrative costs for capital projects. Currently, PCD requires
contractors to hold their price for 60 to 150 days in order to complete administrative tasks
associated with SBOF approval and contract execution. It is uncertain how much this time
requirement increases bid prices, but PCD anticipates savings as small construction contracts are
executed within 30 days of bidding.
SIGNIFICANT ISSUES
SB 555 streamlines the PCD capital project administration process:
It allows the competitive process required by the Procurement Code to be conducted and
a contract signed to retain design firms and set price agreements for construction
contractors for lower dollar projects. As specific projects are ready to begin, the design
or construction companies can be tasked to start work as soon as the scope of work for a
project is identified.
It allows for informal selection of architect and engineering companies for contracts
between $25.0 and $50.0 thus reducing the amount of time it takes to engage a design
firm at project inception.
pg_0003
Senate Bill 555/aSFC – Page
3
It allows smaller construction contracts to be initiated as soon as the low bidder is
determined rather than postponing contract execution for at least a month until the next
SBOF meeting.
PERFORMANCE IMPLICATIONS
SB 555 will expedite PCD project administration and allow earlier project completion.
ADMINISTRATIVE IMPLICATIONS
GSD reports that approximately 78% of PCD construction contracts are less than $500.0 and
most of the work is simple deferred maintenance or life-cycle replacements. SB 555 will allow
expeditious processing for small project contracts.
CONFLICT, DUPLICATION, COMPANIONSHIP, RELATIONSHIP
Relates to SB 264 and HB 277 that establish a $5,000.0 threshold for prior SBOF approval of
projects for the 10 constitutional education institutions after review by the Higher Education
Department.