Fiscal impact reports (FIRs) are prepared by the Legislative Finance Committee (LFC) for standing finance
committees of the NM Legislature. The LFC does not assume responsibility for the accuracy of these reports
if they are used for other purposes.
Current FIRs (in HTML & Adobe PDF formats) are a vailable on the NM Legislative Website (legis.state.nm.us).
Adobe PDF versions include all attachments, whereas HTML versions may not. Previously issued FIRs and
attachments may be obtained from the LFC in Suite 101 of the State Capitol Building North.
F I S C A L I M P A C T R E P O R T
SPONSOR Silva
DATE TYPED 03/12/05 HB 860/aHBIC
SHORT TITLE Lower Design & Build Project Threshold
SB
ANALYST Geisler
APPROPRIATION
Appropriation Contained Estimated Additional Impact Recurring
or Non-Rec
Fund
Affected
FY05
FY06
FY05
FY06
NFI
(Parenthesis ( ) Indicate Expenditure Decreases)
Relates to: SB 897
SOURCES OF INFORMATION
LFC Files
Responses Received From
General Services Department (GSD)
Regulation and Licensing Department (RLD)
Public Schools Facility Authority (PSFA)
SUMMARY
Synopsis of HBIC Amendments
The House and Business and Industry Committee amendments to House Bill 860 clarify that un-
successful firms on the short list and the highest-ranked firm shall be compensated for actual,
documented proposal expenses in an amount not to exceed one percent of total project cost.
Payment shall not entitle an agency to ownership of the documents or ideas represented in the
documents. Payment shall be made to the short listed firms immediately after contract award.
Synopsis of Original Bill
House Bill 860 would add to the public works projects that can use the design and build project
delivery system those projects with an estimated construction cost between $5 million and $10
million.
pg_0002
House Bill 860/aHBIC -- Page 2
Significant Issues
Current law allows using the design/build strategy on public works projects over $10 million es-
timated construction cost, and for projects with a combination of $400,000 or less estimated con-
struction cost that is only for site improvements or for a pre-engineered building. Those smaller
site adapt/site improvement projects must be procured by a competitive sealed bids process
rather than a request for proposal process.
When a design/build system is utilized, the owner contracts with a “team” which includes a de-
sign entity and a construction firm selected through a two-phase request for proposals after a de-
termination that it is appropriate and in the best interest of the state or local public body and
meets specific requirements.
Advantages of Design Build Project Delivery System
PSFA notes that the advantages to the owner of this type of project delivery system include a
single point of contact and responsibility for the entire project. The design/build team also as-
sumes all of the risk for project completion. This significantly reduces the role of the owner in
the process. The owner still has a role in the process in that almost all of the standard contract
forms require the owner to have prepared an “owners program” which sets out the scope of work
and requirements that the owner is looking for.
Another advantage to the owner is there is no “privity of contract” between the designer and the
contractor. This means that the designer and contractor cannot sue each other for design errors
or omissions. And, because the owner has contracted for a higher level of service, the contractor
is often held to warrant the performance of a finished project. Because of the higher standard,
the design /build contractor cannot escape liability merely by proving that construction was in
accordance to project plans and specifications.
Disadvantages of Design Build Project Delivery System
PSFA notes the disadvantage to the owner of this type of project delivery system is that the
owner cannot rely upon the architect to oversee the contractor’s work because the architect is not
the owner’s agent. The architect is the contractor’s partner. The design/build team is usually
given a cost to work within. The motivation to meet the owner’s specifications with the least
cost materials is high because the savings translate to profit for the design/build team. This facet
unfortunately can result in lower overall product quality, higher long term maintenance cost and
shorter building lifecycle relative to traditional design-bid-build process. This effect can be
mitigated somewhat with more detailed “owners program” and specifications but this requires a
very knowledgeable owner. Absent this knowledge the entity may have to spend additional
funds to acquire the services of a construction manager to oversee the performance of the design
build team.
PERFORMANCE IMPLICATIONS
Design/build is a complex project delivery system that requires a knowledgeable user agency or
consultant that can adequately define the project requirements and manage the implementation.
pg_0003
House Bill 860/aHBIC -- Page 3
FISCAL IMPLICATIONS
None identified.
CONFLICT, DUPLICATION, COMPANIONSHIP, RELATIONSHIP
SB 897 and HB 860 both allow design-build on projects between $5 million and $10 million. SB
897 also requires payment of a stipend to the finalist and other short listed offerors equal to one
percent of the project cost.
OTHER SUBSTANTIVE ISSUES
GSD provides that the estimated construction cost is generally about 80 percent of the total pro-
ject cost. The remaining 20 percent is for expenses such as design fees, contingency, consultants
(e.g. environmental, engineering, survey contracts), administration, art-in-public places, gross
receipts taxes on contracts.
PSFA provides that in New Mexico, this authorization does not apply to road and highway con-
struction or reconstruction projects. The cost components that may be included to meet the cost
threshold are: construction costs, architectural/engineering fees, gross receipts tax, utility con-
nections, site development costs, built-in equipment and furnishings and up to ten percent (10%)
project contingency.
WHAT WILL BE THE CONSEQUENCES OF NOT ENACTING THIS BILL.
Requests to use the design/build project delivery system would only be allowed for the large
public works projects with an estimated construction cost of over $10 million.
GG/lg:rs