STATE OF NEW MEXICO
47TH LEGISLATURE - FIRST SESSION - 2005
REQUESTED BY
CAPITAL IMPROVEMENTS IN RUIDOSO
HOUSE CAPITAL OUTLAY REQUEST 0047
I request that the following be funded:
Daniel R. Foley
to the department of environment
•
RUIDOSO SEWER LINE EXTEND-WINGFIELD
three hundred seventy-five thousand dollars ($375,000) to plan, design and construct a sewer
line extension into the Wingfield subdivision area of Ruidoso in Lincoln county
RUIDOSO SOLID WASTE TRANSFER STATION-PH 3
four hundred thousand dollars ($400,000) for phase 3 construction, including additions and a
heating, ventilation and air conditioning system, at the solid waste transfer station in Ruidoso
in Lincoln county
RUIDOSO/RUIDOSO DOWNS TREATMENT PLANT LIFT STATION
one million one hundred seventy thousand dollars ($1,170,000) to plan, design, construct and
equip the phase 1 expansion of the treatment plant jointly owned by Ruidoso and Ruidoso
Downs in Lincoln county
to the department of transportation
•
CARRIZO CANYON RD RESURFACE & WIDEN
three hundred eighty-six thousand dollars ($386,000) to resurface and widen Carrizo Canyon
road from the village limits to the Mescalero Apache Tribe reservation line in Ruidoso in
Lincoln county
CENTER & WINGFIELD STREETS INTERSECT REALIGN
sixty-seven thousand dollars ($67,000) to realign the intersection of Center and Wingfield
streets in Ruidoso in Lincoln county
.05HFOLE014