[1]NOTE:
As provided in LFC policy, this report is intended only for use by the
standing finance committees of the legislature. The Legislative
Finance Committee does not assume responsibility for the accuracy of the information
in this report when used in any other situation.
Only the most recent
FIR version (in HTML & Adobe PDF formats) is available on the Legislative
Website. The Adobe PDF version includes
all attachments, whereas the HTML version does not. Previously issued FIRs and attachments may be obtained from the
LFC’s office in Suite 101 of the State Capitol Building North.
SPONSOR: |
McSorley |
DATE TYPED: |
02/06/02 |
HB |
|
||
SHORT TITLE: |
Renewable Energy Production Tax Credit |
SB |
264 |
||||
|
ANALYST: |
Valenzuela |
|||||
APPROPRIATION
Appropriation
Contained |
Estimated
Additional Impact |
Recurring or Non-Rec |
Fund Affected |
||
FY02 |
FY03 |
FY02 |
FY03 |
|
|
|
$100.0 |
|
|
Recurring |
General Fund |
(Parenthesis
( ) Indicate Expenditure Decreases)
REVENUE
Estimated Revenue |
Subsequent Years
Impact |
Recurring or Non-Rec |
Fund Affected |
|
FY02 |
FY03 |
|
|
|
|
($8,000.0) See
Narrative |
($8,000.0) |
Recurring |
General Fund |
(Parenthesis ( ) Indicate Revenue Decreases)
Duplicates
SB 187
LFC files
Public Regulation Commission (PRC)
Taxation and Revenue Department (TRD)
Energy, Minerals and Natural Resources
Department (EMNRD)
SUMMARY
Synopsis
of Bill
Senate
Bill 264 establishes a tax credit against corporate income tax for developers
of electric generation through renewable energy resources, i.e., generation
produced from low or zero emissions generation technology. Low or zero
emissions generation technology includes solar light, solar heat,
wind,
geothermal, landfill gas, anaerobically digested waste biomass, and fuel cells.
The bill defines a qualified energy generator as a facility with at least 20
megawatts of generation capacity from a qualified energy resource.
This
renewable energy production tax credit is 1.0 cent/KWh for the first 400,000
megawatt-hours produced.
The maximum benefit to any single generator is $4 million
per year; the total incentive program cost is capped at $8 million per year
(800,000 megawatt-hours per year). A generator
may receive the credit for up to ten consecutive years from the production
start date; the credit can be carried forward for five years. The Energy, Minerals and
Natural Resources Department (EMNRD) is appropriated $100.0 to manage a
certification program.
Significant
Issues
In
1999 alone, U.S. wind generation capacity grew by 40 percent, bringing the
nationwide total to 2,500 megawatts (MW).[1] Aside from
being the fastest growing energy source in the world today, the increase in
production is attributed to four main factors: consumer demand for renewable,
or “green” energy; the steadily decreasing cost per kilowatt-hour of
wind-generated electricity; a 1.5 cent/KWh federal production tax credit, and
the increasing reliability of the technology. One result of this new “green”
market has been a boom in the construction of wind power facilities. This boom
provides revenue for rural landowners. Most landowners receive quarterly
payments from wind developers in compensation for wind turbines built on their
property.
New
Mexico’s neighboring states have been especially aggressive in developing wind
power. Texas’ electric industry deregulation law sets a goal of developing
2,000 MW of new renewable energy sources by 2009.
FISCAL IMPLICATIONS
The appropriation of
$100.0 contained in this bill is a recurring expense to the general fund. Any
unexpended or unencumbered balance remaining at the end of FY03 shall revert to
the general fund. The EMNRD further reports that it would require a 0.5 FTE to
administer its certification program.
The maximum revenue impact is a reduction of
$8.0 million to the general fund. It is
not likely that in the first years after enactment the impact would be this
substantial because it would take time for generators to grow its capacity to
the limits identified in the bill. The Taxation and Revenue Department reports
that the impact would approximate to $300.0 reduction to the general fund for
each 40 megawatt facility. The TRD analysis is provided below:
“Estimate shows the annual impacts for a single 40 megawatt (Mwe) facility. The capital cost of the facility is assumed to be $30 million, and equity financing is assumed to represent 50% of this capital. Assuming a 40% availability factor, the facility would generate $1.4 million in tax credits each year, but the corporate tax liability under the above assumptions would be limited to a few hundred thousand dollars per year.”
ADMINISTRATIVE IMPLICATIONS
The administrative
impact would be substantial on the EMNRD and TRD to revise its rules and
processes to be able to certify the generators. EMNRD reports the need for an
additional 0.5 FTE for this purpose.
OTHER SUBSTANTIVE ISSUES
The Public Service
Company of New Mexico recently was reported to be pursuing interests either
directly or through contractual agreements to increase its generation capacity
from wind energy.
POSSIBLE QUESTIONS
How many facilities are estimated to take advantage of this tax credit
within the first five years?
[1]Gagliano, T.:
“Wind Power Development: Policy Options.” National Conference of State Legislatures
State Legislative Report, Vol. 25, Number 12, October 2000.
[1]Begin typing on the * in replace mode. Do not add or delete spaces.