NOTE: As provided in LFC policy, this report is intended for use by the standing finance committees of the legislature. The Legislative Finance Committee does not assume responsibility for the accuracy of the information in this report when used in any other situation.
Only the most recent FIR version, excluding attachments, is available on the Intranet. Previously issued FIRs and attachments may be obtained from the LFC office in Suite 101 of the State Capitol Building North.
SPONSOR: | Ruiz | DATE TYPED: | 02/15/01 | HB | HJM36 | ||
SHORT TITLE: | Interstate 40-Coors Blvd. Interchange Project | SB | |||||
ANALYST: | Valdes |
Recurring
or Non-Rec |
Fund
Affected | ||||
FY01 | FY02 | FY01 | FY02 | ||
See significant issues below. |
(Parenthesis ( ) Indicate Expenditure Decreases)
SOURCES OF INFORMATION
State Highway and Transportation Department
SUMMARY
Synopsis of Bill
House Joint Memorial 36 requests that the State Highway Commission and the State Highway and Transportation Department expedite the construction of the Interstate 40-Coors Boulevard interchange improvement project.
Significant Issues
Funding for construction of this intersection ($11 million) was removed from the Statewide Transportation Improvement Program due to the need to assemble funding for the reconstruction of the Big I interchange.
Funding for project design remains in the program. Final funding requirements will be determined by the design process and are likely to be much higher than $11 million which had previously been programmed.
The I-40-Coors Interchange improvement project is still a priority and will be rescheduled when funding is available.
FISCAL IMPLICATIONS
Funding is currently unavailable for this project within the department budget.
MV/ar/njw