NOTE: As provided in LFC policy, this report is intended for use by the standing finance committees of the legislature. The Legislative Finance Committee does not assume responsibility for the accuracy of the information in this report when used in any other situation.
Only the most recent FIR version, excluding attachments, is available on the Intranet. Previously issued FIRs and attachments may be obtained from the LFC office in Suite 101 of the State Capitol Building North.
SPONSOR: | Pearce | DATE TYPED: | 1/24/00 | HB | 25 | ||
SHORT TITLE: | Recycle Produced Water in Lea County | SB | |||||
ANALYST: | Valenzuela |
Recurring
or Non-Rec |
Fund
Affected | ||||
FY00 | FY01 | FY00 | FY01 | ||
$ 100.0 | Non-recurring | General Fund | |||
(Parenthesis ( ) Indicate Expenditure Decreases)
SOURCES OF INFORMATION
LFC Files
SUMMARY
Synopsis of Bill
House Bill 25 appropriates $100.0 from the general fund for the Oil Conservation Division of the Energy, Minerals and Natural Resources Department (EMNRD) to conduct a research and demonstration project to apply reverse osmosis or another appropriate technology to recycle produced water from oil or gas well drilling. The appropriation would be applicable to projects that occur within Lea County.
Significant Issues
During the process of drilling and producing oil or natural gas, a significant amount of water is produced, which is contaminated with salt and hydrocarbons. Consequently, the water is unusable and must be re-injected back into a subsurface salt zone. This re-injection process is costly and prohibitive when oil prices are low. Researchers have had success in other parts of the country by processing the produced water to a level suitable for boiler operations. House Bill 25 seeks to apply the same technical concepts to production operations in Lea County, as an effort to test the feasibility of this approach.
FISCAL IMPLICATIONS
House Bill 25 will have a one-time non-recurring fiscal impact of $100.0.
ADMINISTRATIVE IMPLICATIONS
The Oil Conservation Division does not employ researchers or scientists, who are capable of carrying out the scope of this project. The division would have to contract this project out.